C3/C5 LACT Upgrades

Project Locations:

  • Near Valleyview, AB

Strike Divisions:

  • Field Services
  • Electric & Instrumentation

Project Overview:

The completion of LACT facility upgrades involved structural steel upgrades, replacement of C3 and C5 pumps and interconnect piping, and installation of new VFDs and MCC upgrades.

Scope

  • Material Procurement
  • Steel Fabrication, Approx 2200kg
  • Piping Fabrication, approx. 1000 FDI
  • New Piling installation
  • Structural steel Demo and upgrade install
  • Piping Demo and Install during scheduled outage time frame
  • Removal and support of installation of New C3/C5 Pumps, including setting and Pump strains
  • Installation of New transformer
  • Demo and Installation of new Cable tray routing
  • New Cable Pulls and Demo of Obsolete
  • Demo, install, and modification of Heat tracing.
  • Install of new VFD’s for Pump control in E-house
  • Install of new MCC in E-House
  • Install of new HVAC unit on E-house
  • Demo and install of Instrument tubing
  • Demo, install, and calibration of Instrumentation